MIL-DTL-83538D
4.5.1.2.2 Lot definition (Group B inspection). The production lot definition as specified in MIL-STD-790
is further defined as follows:
a. A production lot consists of all connectors covered under one military specification or standard,
manufactured from the specified raw materials, processed under the same specification and
procedures, produced by the same type of equipment, and submitted for inspection at one time.
Each production lot of assembled connectors shall be a group identified by a common
manufacturing record through all significant assembly operations.
b. Traceability of connectors to specific physical/chemical test reports of incoming raw material is not
required.
c. Common manufacturing records and traceability shall begin with the start of connector assembly.
TABLE VIII. Group B inspection.
Inspection
Requirement
Test
Number
paragraph
paragraph
of samples
Visual and mechanical examination 1/
See
Shell spring finger forces (receptacles
table IX
with spring fingers only) 1/
1/ The contractor may use in-house controls for this requirement.
TABLE IX. Sampling plans.
Lot size
Sample size
1 to 13
100 percent
14 to 150
13 units
151 to 280
20 units
281 to 500
29 units
501 to 1,200
34 units
1,201 to 3,200
42 units
4.5.1.2.3 Disposition of sample units. Sample units which have passed all of group B inspections may
be delivered on the contract or purchase order if the lot is accepted and the sample units are still within
specified tolerances.
4.5.2 Periodic inspection. Periodic inspection shall consist of group C inspection. Except where the
results of this inspection show noncompliance with the applicable requirements (see 4.5.2.1.4), delivery
of products which have passed groups A and B inspections shall not be delayed pending the results of
this periodic inspections.
4.5.2.1 Group C inspection. Periodic tests for group C inspections shall be performed on a 12-month
and 24-month basis, beginning with the 12-month periodic test, which must be accomplished within this
period after notification of qualification and alternating thereafter with the 24-month periodic test.
Samples submitted to either of these periodic tests shall have passed groups A and B inspections.