MIL-DTL-83513/5H
REQUIREMENTS:
Dimensions and configurations: See figure 1 through 4.
Material and finish:
Jackscrew: Shall be corrosion resistant steel, nonmagnetic corrosion resistant steel having a
minimum tensile strength of 125,000 psi.
Jackpost and nut: Corrosion resistant steel in accordance with ASTM A484/A484M and either
ASTM A276 or ASTM A582/A582M, passivated in accordance with SAE-AMS-2700.
Clip and washers: Corrosion resistant steel in accordance with ASTM A 240/A240M; passivated in
accordance with SAE-AMS-2700. Does not meet the 2.0 µ permeability requirements of the basic
specification.
Application:
Mounting hardware not furnished with connectors. All dash numbers fit configurations A and B
connectors only (MIL-DTL- 83513/01 through MIL-DTL-83513/04 and MIL-DTL-83513/06 through
MIL-DTL-83513/09, except for configuration C which is for 100 cavity arrangement only and uses No.
4-40 mounting hardware. Two complete assemblies as shown are supplied with each dash number.
Installation:
M38513/05-02, -03, -05, -06, -12, -13, -15, and -16 jackscrew with retaining ring: Place jackscrew
(either slotted or hex, long or low profile types) through mounting hole in connector flange then slide
retaining ring into slot in jackscrew.
M83513/05-07 and -17 jackpost: Place jackpost through mounting hole in connector flange and
mounting panel (if used). Place lockwasher over screw threads then screw on nut and torque as
required.
Qualification of hardware only: To obtain qualification of hardware only, the hardware shall be installed
on a qualified connector and shall be subjected to the tests below in accordance with MIL-DTL-83513.
Sample size, if qualifying all hardware configurations, shall be four connector pairs. One sample with
hardware installed from configuration A and B low profile, one sample with hardware installed from
configurations A and B high profile, One sample with hardware installed from configuration C low
profile, and one sample with hardware installed from configuration C high profile.
Visual and mechanical inspection
Vibration
Shock
Salt spray"
PIN: See figures 1 through 4.
Changes from previous issue. The margins of this specification are marked with vertical lines to indicate
where changes from the previous issue were made. This was done as a convenience only and the
Government assumes no liability whatsoever for any inaccuracies in these notations. Bidders and
contractors are cautioned to evaluate the requirements of this document based on the entire content
irrespective of the marginal notations and relationship to the last previous issue.